Order Hrs vs Actual Hrs

Post by Gerald Martin »

Is there a quick way to visualize the tech's efficiency on a per-work-order basis? For instance, the order screen displays total labor hrs. Where can we see a total of actual hrs (if the techs are clocking in and out on labor items using Mobile Manager?)

Maybe the answer is hiding in plain sight.

Gerald
Gerald Martin
50 Club: Regular Contributor
50 Club: Regular Contributor
Posts: 95
Joined: Wed Oct 22, 2008 8:56 am

Re: Order Hrs vs Actual Hrs

Post by Gerald Martin »

Anyone?
User avatar
Pauls Automotive
1000 Club: Interstellar
1000 Club: Interstellar
Posts: 1415
Joined: Wed May 24, 2006 6:32 am
Location: Baltimore Maryland
Contact:

Re: Order Hrs vs Actual Hrs

Post by Pauls Automotive »

I don't know of any quick way within Mitchell short of manually making the calculations. I ended up using a third party program that is a time clock that the guys sign in for the day but also per job that integrates with Mitchell and gives me all those numbers. It is called Labor Profit Management.. If that is of any help.
Paul
Pauls Automotive
6318 Falls Road
Baltimore, Md 21209
410-825-2224
paul@paulsauto.com
TRUE HAPPINESS IS WITHIN YOU
User avatar
timbre4
System Guru / Moderator
System Guru / Moderator
Posts: 4456
Joined: Tue May 25, 2004 5:47 pm
Location: TN - Volunteer State

Re: Order Hrs vs Actual Hrs

Post by timbre4 »

Gerald Martin wrote:Is there a quick way to visualize the tech's efficiency on a per-work-order basis? For instance, the order screen displays total labor hrs. Where can we see a total of actual hrs (if the techs are clocking in and out on labor items using Mobile Manager?)
Maybe the answer is hiding in plain sight.
Gerald
That data is not being written back to storage in SE; if any reporting was to be available it would be in their ReportPro portfolio.

Since MM Pro / time clock is referenced, I am moving this to their topic area.
Tim McDonnell -
Sr. Product Market Mgr / Forum Moderator / Mitchell 1 Media Developer
User avatar
Auto Repair Coach
400 Club: Mega-Star Contributor
400 Club: Mega-Star Contributor
Posts: 425
Joined: Wed Sep 07, 2016 11:21 am
Location: Southampton Pa.
Contact:

Re: Order Hrs vs Actual Hrs

Post by Auto Repair Coach »

Currently, without using the Labor Profit Management Software mentioned above, there is no way in Mobile Manager to automatically calculate tech efficiencies. No data is written since there is no place to put it at this time. No data, no reports. (Example. Where would tech punch in and out for the day go?)