Acct Scenario- Partial credit on a bill after being paid

Post Reply
M1EnterpriseTech
100 Club: Active Contributor
100 Club: Active Contributor
Posts: 171
Joined: Wed Aug 24, 2016 9:22 am

Acct Scenario- Partial credit on a bill after being paid

Post by M1EnterpriseTech »

It is recommended that you reach out to Enterprise Support if you have any questions.

The attached document is based on the following accounting scenario in Enterprise Pro:

Shop purchased office supplies.
Shop created Bill to post to suppliers payable account for the office supplies using General Office expense account.
Shop made payment in full to supplier using shop credit card.
Shop returned items to supplier for partial credit.
Supplier issued credit to the shop credit card used for purchase.

How to get these transactions to reflect in Enterprise Pro? See attached document:
Attachments
Accounting Scenario.docx
(18.67 KiB) Downloaded 170 times
Enterprise Support Specialist
Post Reply

Return to “Enterprise: Accounting”